December 8, 2020 - Public Meeting Minutes
Passcode: ?4UT4+w@
- Introduction
- Project
team introductions
i. Corvus
– landscape architect and meeting facilitator
1.
Peter Briggs, landscape architect
2.
Linda Pringle, landscape architect
ii. PND
– designer
1.
Paul Kendall, contract manager/lead civil
2.
Alex Jefferies, project manager
3.
Anna Kopitov, NEPA coordinator
iii. FWS
– owner
1.
Amy Klein, project manager
2.
Steve Miller, Kenai National Wildlife Refuge Deputy
Manager
- Housekeeping
i. Meeting
was recorded
ii. Introduction
of project website: www.usfws-jims.blogspot.com
iii. Comments
and questions to be saved until end of meeting
- Project
purpose and need
i. Project
location within the Skilak Wildlife Recreation Area in the Kenai National
Wildlife Refuge
ii. USFWS
has identified the need for improvements to the ramp and parking areas to
address deficiencies such as:
1.
High velocities at the ramp
2.
General congestion
3.
Limited parking capacity
- Review of the site’s existing conditions
- Presentation
of Options
- Options
A-C
i. Options
generated for review and to solicit comments on various components. Pieces of
each option can be used with others
ii. Generally
discussed differences and impacts of each option
iii. Option
A provides least impact to the environmental (similar to existing conditions),
but makes the fewest improvement to the traffic circulation.
iv. Option
B shows a slightly larger area of impact, and pushing closer to riparian area.
Provides linear trailer parking and provides significant improvements to
traffic circulation while prioritizing non-trailer parking near the ramp.
v. Option
C shows the largest impacts, particularly into the wetlands. Prioritizes
trailer parking near the ramp. Parking and circulation more similar to Sportsman’s.
- Offsite
parking options 1-2
i. Offsite
parking options along Skilak Lake Road with option for trails through wooded
area to connect parking to Jim’s Landing.
ii. Shown
with Option A since adequate parking is provided for Options B & C onsite,
but could be combined with these options as well.
- Ramp
area improvements
i. Not
really shown on the drawings, but options that are being considered:
1.
Articulated concrete block mat surfacing
(similar to Sportsman’s Boat Launch)
2.
32-foot wide ramp area
3.
Addition of tie-offs on either side of the active
ramp
4.
Installation of rootwad structures for bank
stabilization and local velocity reduction upstream of ramp
5.
Extension of the ramp improvement area
downstream for additional landing and staging area
6.
Potentially pulling ramp inland and creating a
backwater basin
ii. These are all being considered and additional analysis is currently being completed to assess feasibility of the various options.
- Procedures
of submitting comments
- Link
to comment collector (Survey Monkey) can be found on the project website.
- May also
leave verbal comment as a voicemail by calling (907) 646-2784
- Environmental
Assessment Schedule
- Currently
in schematic design, and the developed designs were made to solicit
public comments
- Scoping
comment period opens now, ends January 8th
- A second public meeting and associated comment period are tentatively scheduled for mid-March
- Miscellaneous
a. Discussed
previous evaluation in the area. Wanted to note that previous alternatives were
assessed in the past (and not here). These included options, such as a loop
road that would encroach into riparian areas, or crossing Jean Creek. In order
to minimize these impacts, these options were discarded
b. Offsite
parking areas were selected to avoid wetland areas
c. Reiterate that the schematics were developed to show a wide range of options, and that different components can be used with the other alternative components to create a preferred alternative.
- Q&A Summary
- Not a design question but a usage question: with the
additional spaces, would this mean commercial operators/guides will be
allowed to park in the new area, or will they park in the new overflow
areas off of Skilak Rd? Currently only private users can park at Jims
- Secondary parking as permit parking—parking closest to the
ramp for public
- Steve Miller—no decision has been made at the moment.
Priority is safety, and limiting the number of people to cross the Sterling
Hwy (especially with the improvements). Likely the ones closest to the
ramp would be for public
- You may have mentioned: (1)is construction funded and, if
so, what is the timeline for construction? (2) You showed that the boat
launch area may be hardened, would the driving surface remain gravel or be
paved?
- 1) construction is not currently funded—not designed yet
- Funding potentially in 2021 or 2022. It is also a
ADF&G Sportfish Division project. USFWS and ADF&G looking for
funding concurrently.
- 2) Will be assessed during design. See Schematic Design
Report on the website for concept-level cost estimate
- I have a few questions to establish comparison: How many
truck/trailer spaces exist at the existing Jim’s overflow parking across
the sterling highway? How long is the Sportsman’s landing in comparison to
the existing Jims’s Landing listed in the documents as 90’ long? How many
boat tie ups are considered to be located on either side of Sportsman’s
right now? What is the plan for the existing overflow parking? What would
be the intended windows of construction?
- Not sure on the existing number of parking across Sterling
- Sporstmans: 90’
- Boat tie ups: unsure
- Existing overflow parking: no plans; still overflow parking
- The current design for the ramp only shows one to two boats on
the ramp at a time, the current ramp system allows for 5 to 7 boats at a
time, that’s not enough to handle the needs for the ramp, during the heavy
weekend traffic?
- Trying to increase flow, but can’t hit peak; assisting with
flow and congestion
- Currently shown as double the width as Sportsmans (on the
active area)
- Is someone from the design team going to observe the ramp
during Salmon runs this summer?
- Members from the design team will be onsite, and have
onsite experience throughout the season
- Starting construction in 2021?
- Design wrap up next fall, so observations will be made
onsite. Construction TBD
- If construction will be necessary during the summer, is site
access planned to be maintained during this construction and can you
expand on how that would be maintained?
- Construction will be necessary during the summer, but has
not been thought through thoroughly at this point. It is a significant
logistics concern.
- Need to balance use and project cost.
- This will be an important thing to assess in the future,
and feedback is important.
- Jims landing really needs some break water to create an eddy
safely land boats. a small rock
vein on the upper most section would be great. could you give some details?
- A jetty is not permittable in the Kenai River. Other options
are being considered to reduce velocities.
- Would be good to get comments on use of rootwads upstream
of the ramp
- Will there be additional comment periods for the different
phases of planning once a preferred option is chosen so that responses to
the preferred alternative can be incorporated once others know what the plan
is?
- Yes—after the draft EA in mid-March
- How about an area for people who come just to looky
loo. Sportsmans has a nice viewing
platform?
- Good comment
- Potential interpretive signs
- Adding parking for those people
- Speaking of signage—discussed adding sign upstream of ramp for landing warning
- Summary of Comments:
- As much staging area as possible for people waiting for
their boats to arrive.
- Option B – wheel stops will be required, and should be
placed on the south side, but could mix some of the parking with the wheel
stops on the north side to add additional tie-down area. Jim’s sees roughly
90% for retrieval/10% launching, so prioritize pull-in parking from coming
into the ramp.
- An expanded area for landing is needed.
- Multiple people suggested area upstream of active ramp for
landing.
- “Hail Mary” zone needed downstream for last chance landing
area.
- Minimizing impacts to user access during construction in an
important concern of the project. Attendees were polled to determine the Ideal
construction period which may include closures:
- Four supported April/May
- Two supported May 1 to June 11
- One supported late October into November
- Summary
& Next Steps
- Comment
period open through January 8, 2021
- Project
team will be working on the Environmental Assessment and developing the alternatives
based on this scoping
- Environmental
Assessment will be released to the public for review, with another public
meeting and comment period tentatively scheduled for mid-March 2021
- Updates will be posted on the project website